MISO-J2750
197.5 MW generation in Phillips, AR · In queue since September 2022 · Proposed COD January 2026
197.5 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 4m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-01
MISO-J2750 is a proposed solar generation project with a total capacity of 197.5 MW. The project is located in Phillips County, Arkansas, and is being developed within the Entergy Arkansas service area. It entered the Midcontinent Independent System Operator (MISO) interconnection queue on September 15, 2022, with a proposed commercial operation date of January 1, 2026.
The interconnection agreement for MISO-J2750 is currently listed as "In Progress (unknown study)". The point of interconnection is the 230kV Ritchie SES Switchyard - Tarleton line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
AR
County
Phillips
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
230kV Ritchie SES Switchyard - Tarleton line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Kirk Switchyard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2750