MISO-J2751
175 MW generation in Bolivar, MS · In queue since September 2022 · Proposed COD January 2026
175 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 4m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-01
MISO-J2751 is a proposed solar generation project with a total capacity of 175 MW, located in Bolivar County, Mississippi. The project is being developed within the Entergy Mississippi service area and interconnected to the 115kV Stringtown substation.
The project entered the MISO interconnection queue on September 14, 2022, with a proposed commercial operation date of January 1, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
MS
County
Bolivar
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
—
Point of Interconnection
115kV Stringtown substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2751