MISO-J2754
170 MW generation in Polk, TX · In queue since September 2022 · Proposed COD January 2026
170 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 4m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-01
MISO-J2754 is a proposed solar generation project with a total capacity of 170 MW, located in Polk County, Texas. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 15, 2022. The proposed commercial operation date is January 1, 2026. The project's interconnection agreement status is listed as "In Progress (unknown study)".
The project, which is being developed within the Entergy Texas, Inc. service area, consists of 170 MW of solar photovoltaic generation. The point of interconnection is the 138kV Bragg - SHECO Menard Line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Polk
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY TEXAS, INC.
Entity
MISO
Service Type
—
Point of Interconnection
138kV Bragg - SHECO Menard Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- TEXAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.