MISO-J2757
160.3 MW generation in Cherokee, IA · In queue since September 2022 · Proposed COD May 2026
160.3 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
3y 8m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-01
MISO-J2757 is a proposed solar generation project with a total capacity of 160.3 MW, located in Cherokee County, Iowa. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, under queue ID MISO-J2757, with an entry date of September 15, 2022. The proposed commercial operation date is May 1, 2026. The interconnection status is currently in the Cluster Study phase. The interconnecting utility is MidAmerican Energy Co.
The proposed project consists of 160.3 MW of solar photovoltaic generation. The point of interconnection (POI) is Little Sioux - Clipper. The project is listed as active in the MISO queue.
Generated from interconnection queue and public data sources
State
IA
County
Cherokee
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MIDAMERICAN ENERGY CO.
Entity
MISO
Service Type
—
Point of Interconnection
Little Sioux - Clipper
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.