MISO-J2759
170 MW generation in Arkansas, AR · In queue since September 2023 · Proposed COD September 2026
170 MW
Capacity
1
Components
Solar
2y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
MISO-J2759 is a proposed solar generation project with a total capacity of 170 MW, located in Arkansas County, Arkansas. The project is in the MISO interconnection queue, having entered the queue on September 12, 2023. Entergy Arkansas is the interconnecting utility. The proposed commercial operation date is September 1, 2026, and the interconnection agreement status is listed as "In Progress (unknown study)".
The project consists of 170 MW of solar generation. The point of interconnection is the Woodward-Ricuskey 230 kV Line. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AR
County
Arkansas
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
Woodward-Ricuskey 230 kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2759