MISO-J2761
100 MW generation in Marion, MS · In queue since September 2022 · Proposed COD September 2025
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3 years
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-30
MISO-J2761 is a proposed 100 MW solar generation project located in Marion County, Mississippi. The project, under development by Cooperative Energy, entered the Midcontinent Independent System Operator (MISO) interconnection queue on September 15, 2022. Its proposed commercial operation date is September 30, 2025. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project consists of 100 MW of solar photovoltaic generation. The point of interconnection (POI) is at the Columbia substation. The project is currently listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
MS
County
Marion
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
COOPERATIVE ENERGY
Entity
MISO
Service Type
—
Point of Interconnection
Columbia
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MGE.JOUCOLUM1
- POI Substation
- Columbia Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.