MISO-J2763
100 MW hybrid in Sunflower, MS · In queue since September 2022 · Proposed COD December 2025
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 3m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-06
MISO-J2763 is a proposed 100 MW hybrid solar and battery energy storage project located in Sunflower County, Mississippi. The project, which consists of 100 MW of solar capacity, is in the Midcontinent Independent System Operator (MISO) interconnection queue. It was entered into the queue on September 14, 2022, with a proposed commercial operation date of December 6, 2025. The interconnecting utility is Entergy Mississippi, LLC.
The interconnection agreement (IA) status for MISO-J2763 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Cleveland/South - Steiner (CE) 115.0kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
MS
County
Sunflower
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
—
Point of Interconnection
CLEVELAND/SOUTH - STEINER (CE) 115.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2763