Project MISO-J2773 — Project Summary

Queue ID
MISO-J2773
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Poinsett, AR
Region
MISO
Developer
IA Status

MISO-J2773

MISO-J2773BetaActiveSolarBatteryMISOLBNL + Live

100 MW hybrid in Poinsett, AR · In queue since September 2022 · Proposed COD June 2027

100 MW

Capacity

1

Components

Solar

3y 8m

In Queue

IA Status

COD target: 2027

Interconnection

Total Duration

4y 9m

Pre-Study0%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

About

MISO-J2773 is a proposed 100 MW hybrid solar and battery project located in Poinsett County, Arkansas. The project, which consists of 100 MW of solar generation, is interconnected within the Midcontinent Independent System Operator (MISO) queue. The project's point of interconnection is the Newport - Fisher 161 kV Line.

The project entered the MISO interconnection queue on September 15, 2022, with a proposed commercial operation date of June 1, 2027. The utility is Entergy Arkansas.

Generated from interconnection queue and public data sources

Project Details

State

AR

County

Poinsett

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

ENTERGY ARKANSAS

Entity

MISO

Service Type

Point of Interconnection

Newport - Fisher 161 kV Line

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
ARKANSAS.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.