MISO-J2773
100 MW hybrid in Poinsett, AR · In queue since September 2022 · Proposed COD June 2027
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
—
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
MISO-J2773 is a proposed 100 MW hybrid solar and battery project located in Poinsett County, Arkansas. The project, which consists of 100 MW of solar generation, is interconnected within the Midcontinent Independent System Operator (MISO) queue. The project's point of interconnection is the Newport - Fisher 161 kV Line.
The project entered the MISO interconnection queue on September 15, 2022, with a proposed commercial operation date of June 1, 2027. The utility is Entergy Arkansas.
Generated from interconnection queue and public data sources
State
AR
County
Poinsett
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
Newport - Fisher 161 kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2773