MISO-J2786
189.25 MW hybrid in Allegan, MI · In queue since September 2022 · Proposed COD July 2024
189.25 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 10m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-07-01
MISO-J2786 is a proposed hybrid solar and battery project with a total capacity of 189.25 MW. The project is located in Allegan County, Michigan, and is interconnected within the Midcontinent Independent System Operator (MISO) region. The queue entry date is September 15, 2022, with a proposed commercial operation date of July 1, 2024. The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the ARGENTA - TALLMADGE 345.0kV line.
The project, developed under the utility METC, consists of 189.25 MW of solar capacity. The project is listed as active in the MISO interconnection queue. The project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
State
MI
County
Allegan
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
ARGENTA - TALLMADGE 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2786