MISO-J2801
130 MW generation in Woodruff, AR · In queue since September 2023 · Proposed COD September 2026
130 MW
Capacity
1
Components
Solar
2y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
MISO-J2801 is a proposed solar generation project located in Woodruff County, Arkansas, within the Midcontinent Independent System Operator (MISO) region. The development project, with a total capacity of 130 MW, is being proposed by Entergy Arkansas. It consists of 130 MW of solar photovoltaic generation.
The project entered the MISO interconnection queue on September 11, 2023, and has a proposed commercial operation date of September 1, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the AECC Hunter North-McCrory 161 kV substation.
Generated from interconnection queue and public data sources
State
AR
County
Woodruff
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
AECC Hunter North-McCrory 161 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2801