MISO-J2806
200 MW generation in Warren, MO · In queue since September 2022 · Proposed COD September 2026
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
MISO-J2806 is a proposed solar generation project located in Warren County, Missouri, with a total capacity of 200 MW. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue under queue ID MISO-J2806. The queue entry date is September 13, 2022, and the proposed commercial operation date is September 1, 2026. Ameren Missouri is the utility associated with the project.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the Warrenton 161kV Substation.
Generated from interconnection queue and public data sources
State
MO
County
Warren
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Service Type
—
Point of Interconnection
Warrenton 161kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Warrenton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2806