MISO-J2808
100 MW generation in Fayette, IL · In queue since September 2022 · Proposed COD September 2026
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
The proposed project MISO-J2808 is a 100 MW solar generation project located in Fayette County, Illinois. It is interconnected within the Midcontinent Independent System Operator (MISO) region, with Ameren Illinois as the utility. The project entered the MISO interconnection queue on September 14, 2022, and has a proposed commercial operation date of September 1, 2026. Its interconnection status is currently in the Cluster Study phase.
The point of interconnection (POI) for the project is the Ramsey East 138 kV substation, co-located with the Dressor and Switchgrass projects.
Generated from interconnection queue and public data sources
State
IL
County
Fayette
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Ramsey East 138 sub (co-located with Dressor and Switchgrass)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Ramsey
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2808