MISO-J2812
150 MW generation in Hillsdale, MI · In queue since September 2022 · Proposed COD September 2026
150 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
MISO-J2812 is a proposed solar generation project located in Hillsdale County, Michigan, with a total capacity of 150 MW. The project, under consideration in the Midcontinent Independent System Operator (MISO) interconnection queue, entered the queue on September 14, 2022, and has a proposed commercial operation date of September 1, 2026. The interconnecting utility is METC.
The interconnection agreement (IA) for MISO-J2812 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Moore Road 138kV Substation.
Generated from interconnection queue and public data sources
State
MI
County
Hillsdale
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Moore Road 138kV Sub
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Moore Road Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2812