MISO-J2814
220 MW generation in Kalamazoo, MI · In queue since September 2022 · Proposed COD February 2026
220 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
3y 5m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-02-15
MISO-J2814 is a proposed solar generation project located in Kalamazoo County, Michigan, with a total capacity of 220 MW. The project is being developed within the Midcontinent Independent System Operator (MISO) region and interconnected to the Argenta Morrow 138 kV point of interconnection. The queue entry date for MISO-J2814 is September 7, 2022, with a proposed commercial operation date of February 15, 2026. Its interconnection status is currently in the Cluster Study phase.
The project is sponsored by METC. It is listed as an active project in the MISO interconnection queue.
Generated from interconnection queue and public data sources
State
MI
County
Kalamazoo
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Argenta Morrow 138 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2814