MISO-J2816
100 MW generation in Ouachita Parish, LA · In queue since September 2022 · Proposed COD March 2025
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 6m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-31
MISO-J2816 is a proposed solar generation project with a total capacity of 100 MW, located in Ouachita Parish, Louisiana. The project is being developed within the Entergy Louisiana service area and interconnected to the Midcontinent Independent System Operator (MISO) grid at the Rilla (Endpoint A) - Riverton (Endpoint B) point of interconnection.
The project entered the MISO interconnection queue on September 8, 2022, with a proposed commercial operation date of March 31, 2025. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The project consists of 100 MW of solar photovoltaic generation.
Generated from interconnection queue and public data sources
State
LA
County
Ouachita Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY LOUISIANA
Entity
MISO
Service Type
—
Point of Interconnection
Rilla (Endpoint A) - Riverton (Endpoint B)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Riverton
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.