250 MW storage in Van Buren, MI · In queue since September 2022 · Proposed COD March 2025
250 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 6m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-01
MISO-J2822 is a proposed 250 MW battery storage project located in Van Buren County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on September 8, 2022. The proposed commercial operation date is March 1, 2025. The project's interconnection agreement status is listed as "In Progress (unknown study)". The interconnecting utility is METC.
The development project consists solely of battery storage, with a total capacity of 250 MW. The point of interconnection is the Palisades - Vergennes 345 kV line. The project has appeared in recent news coverage regarding energy storage development in the MISO region.
Generated from interconnection queue and public data sources
State
MI
County
Van Buren
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Palisades - Vergennes 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.