MISO-J2826
200 MW hybrid in Greene, IN · In queue since September 2022 · Proposed COD June 2027
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
MISO-J2826 is a proposed 200 MW hybrid solar and battery project located in Greene County, Indiana. The development project, with Hoosier Energy listed as the utility, consists of 200 MW of solar capacity. It is actively listed in the Midcontinent Independent System Operator (MISO) interconnection queue, with a queue entry date of September 15, 2022, and a proposed commercial operation date of June 1, 2027.
The interconnection status for MISO-J2826 is currently in the Cluster Study phase. The point of interconnection (POI) is the Worthington (07WORTH) - Sandborn Primary (07SAND61) 161kV location. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
IN
County
Greene
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
HOOSIER ENERGY
Entity
MISO
Service Type
—
Point of Interconnection
Worthington (07WORTH) - Sandborn Primary (07SAND61) 161kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.