MISO-J2841
500 MW generation in Independence, AR · In queue since September 2022 · Proposed COD October 2025
500 MW
Capacity
1
Components
Wind
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 1m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-01
The proposed MISO-J2841 project is a 500 MW wind generation facility located in Independence County, Arkansas. The project, which is in the Entergy Arkansas service area, entered the MISO interconnection queue on September 15, 2022, with a proposed commercial operation date of October 1, 2025.
The interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Independent - Holland Bottom 500kV substation.
Generated from interconnection queue and public data sources
State
AR
County
Independence
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
Independent - Holland Bottom 500kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ALTE.ONIONRIV
- POI Substation
- Holland
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.