MISO-J2845
200 MW generation in Freeborn, MN · In queue since September 2022 · Proposed COD October 2025
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
3y 1m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-15
MISO-J2845 is a proposed 200 MW solar generation project located in Freeborn County, Minnesota. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on September 15, 2022. The proposed commercial operation date is October 15, 2025. The project's interconnection status is currently in the Cluster Study phase, and the point of interconnection is the Hayward - Adams 161kV line.
The project is being developed within the ITC MIDWEST utility territory. The project consists of 200 MW of solar photovoltaic generation.
Generated from interconnection queue and public data sources
State
MN
County
Freeborn
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
—
Point of Interconnection
Hayward - Adams 161kV line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2845