MISO-J2847
180 MW generation in Starke, IN · In queue since September 2022 · Proposed COD August 2026
180 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-08-01
MISO-J2847 is a proposed solar generation project with a total capacity of 180 MW, located in Starke County, Indiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on September 15, 2022. The proposed commercial operation date is August 1, 2026.
The project's interconnection status is currently in the Cluster Study phase. Northern Indiana Public Service Company is listed as the utility. The point of interconnection (POI) is the Reynolds--Burr Oak 345kV Line.
Generated from interconnection queue and public data sources
State
IN
County
Starke
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Reynolds--Burr Oak 345kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2847