MISO-J2849
245 MW generation in Pulaski, IN · In queue since September 2022 · Proposed COD December 2025
245 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
3y 3m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
MISO-J2849 is a proposed solar generation project with a total capacity of 245 MW, located in Pulaski County, Indiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 15, 2022. Northern Indiana Public Service Company is the utility associated with the project.
The proposed commercial operation date is December 1, 2025. The project's interconnection status is currently in the Cluster Study phase and will connect to the Reynolds--Burr Oak 345kV line.
Generated from interconnection queue and public data sources
State
IN
County
Pulaski
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Reynolds--Burr Oak 345kV line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2849