MISO-J2866
375 MW generation in Nevada, AR · In queue since September 2022 · Proposed COD August 2027
375 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-31
MISO-J2866 is a proposed solar generation project with a total capacity of 375 MW, located in Nevada County, Arkansas. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 13, 2022. Entergy Arkansas is the interconnecting utility. The proposed commercial operation date is August 31, 2027, and the interconnection agreement status is listed as "In Progress (unknown study)".
The project consists of 375 MW of solar photovoltaic generation. The point of interconnection is the McNeil 500kV (A) to Etta 500kV (B) transmission line.
Generated from interconnection queue and public data sources
State
AR
County
Nevada
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
McNeil 500kV (A) to Etta 500kV (B)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2866