MISO-J2868
46.2 MW generation in Jackson, WI · In queue since September 2022 · Proposed COD December 2026
46.2 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
MISO-J2868 is a proposed solar generation project with a total capacity of 46.2 MW, located in Jackson County, Wisconsin. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on September 15, 2022. Wolverine Power Supply Cooperative is the utility associated with the project. The proposed commercial operation date is December 1, 2026, and its interconnection status is currently in the Cluster Study phase.
The proposed project consists of 46.2 MW of solar photovoltaic generation. The point of interconnection is the Alma Center- Merrillan (DCP) 69 KV line. The project is currently listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
WI
County
Jackson
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
WOLVERINE POWER SUPPLY COOPERATIVE
Entity
MISO
Service Type
—
Point of Interconnection
Alma Center- Merrillan (DCP) 69 KV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2868