MISO-J2869
150 MW hybrid in Sunflower, MS · In queue since September 2022 · Proposed COD June 2027
150 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
MISO-J2869 is a proposed 150 MW hybrid solar and battery project located in Sunflower County, Mississippi. The development project, which consists of 150 MW of solar capacity, is in the Midcontinent Independent System Operator (MISO) interconnection queue. Entergy Mississippi, LLC. is the interconnecting utility.
The project entered the MISO queue on September 15, 2022, with a proposed commercial operation date of June 1, 2027. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Gerald Andrus SES Switchyard-Indianola 230 kV. The project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
State
MS
County
Sunflower
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
—
Point of Interconnection
GERALDANDRUS SES SWITCHYARD-INDIANOLA 230 KV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2869