MISO-J2873
200 MW generation in Simpson, MS · In queue since September 2022 · Proposed COD October 2027
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-01
MISO-J2873 is a proposed 200 MW solar generation project located in Simpson County, Mississippi. The project, developed by Cooperative Energy, entered the Midcontinent Independent System Operator (MISO) interconnection queue on September 13, 2022. Its proposed commercial operation date is October 1, 2027.
The interconnection agreement for MISO-J2873 is currently listed as "In Progress (unknown study)". The point of interconnection is the Magee - White Oak 161kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
MS
County
Simpson
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
COOPERATIVE ENERGY
Entity
MISO
Service Type
—
Point of Interconnection
Magee - White Oak 161kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2873