MISO-J2874
85 MW generation in Bay, MI · In queue since August 2022 · Proposed COD November 2025
85 MW
Capacity
1
Components
Solar
3y 9m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
3y 3m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-15
MISO-J2874 is a proposed solar generation project located in Bay County, Michigan, with a total capacity of 85 MW. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on August 31, 2022. Its proposed commercial operation date is November 15, 2025. The interconnection point is the METC Hampton 345 kV substation. The project's interconnection status is currently in the Cluster Study phase.
The development project is sponsored by Michigan Electric Transmission Company (METC). It consists of 85 MW of solar photovoltaic generation. The project is currently listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
MI
County
Bay
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
METC Hampton 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2874