MISO-J2875
150 MW generation in Presque Isle, MI · In queue since September 2022 · Proposed COD November 2025
150 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 2m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-01
MISO-J2875 is a proposed solar generation project with a total capacity of 150 MW, located in Presque Isle County, Michigan. The project is being developed within the Midcontinent Independent System Operator (MISO) region and is interconnected with METC at the Port Calcite- Rockport 138 KV point of interconnection.
The project entered the MISO interconnection queue on September 14, 2022, with a proposed commercial operation date of November 1, 2025. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
MI
County
Presque Isle
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Port Calcite- Rockport 138 KV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2875