MISO-J2877
200 MW generation in Midland, MI · In queue since September 2022 · Proposed COD November 2025
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
3y 2m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-01
MISO-J2877 is a proposed solar generation project located in Midland County, Michigan, with a total capacity of 200 MW. The project, interconnected within the Midcontinent Independent System Operator (MISO) region, entered the MISO queue on September 14, 2022, with a proposed commercial operation date of November 1, 2025. The project's interconnection point is the Murphy-Tittabawassee 345kV Transmission Line. Its interconnection status is currently in the Cluster Study phase.
The development project is sponsored by Michigan Electric Transmission Company (METC). The project consists of 200 MW of solar photovoltaic generation.
Generated from interconnection queue and public data sources
State
MI
County
Midland
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Murphy-Tittabawassee 345kV Transmission Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2877