MISO-J2885
130 MW generation in Red Lake, MN · In queue since September 2022 · Proposed COD January 2025
130 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
2y 4m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-01-10
MISO-J2885 is a proposed 130 MW solar generation project located in Red Lake County, Minnesota. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 6, 2022. Otter Tail Power Company is the interconnecting utility. The proposed commercial operation date is January 10, 2025.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is Plummer Pipe.
Generated from interconnection queue and public data sources
State
MN
County
Red Lake
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
OTTER TAIL POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Plummer Pipe
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2885