MISO-J2893
200 MW hybrid in Holmes, MS · In queue since September 2022 · Proposed COD August 2027
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-18
MISO-J2893 is a proposed 200 MW hybrid solar and battery energy storage project located in Holmes County, Mississippi. The project, which consists of 200 MW of solar generation, is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an interconnection queue entry date of September 15, 2022. The proposed commercial operation date is August 18, 2027. The interconnecting utility is Entergy Mississippi, LLC.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Bowling Green SS - Durant 115 kV substation.
Generated from interconnection queue and public data sources
State
MS
County
Holmes
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
—
Point of Interconnection
Bowling Green SS - Durant 115 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM