MISO-J2897
150 MW hybrid in San Jacinto, TX · In queue since September 2022 · Proposed COD April 2025
150 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 7m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-04-30
MISO-J2897 is a proposed 150 MW hybrid solar and battery project located in San Jacinto County, Texas. The project consists of 150 MW of solar generation. It is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 15, 2022, and a proposed commercial operation date of April 30, 2025. The interconnecting utility is Entergy Texas, Inc.
The interconnection agreement (IA) status for MISO-J2897 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Rivtrin - Staley 138kV Line #2 (Southern Line).
Generated from interconnection queue and public data sources
State
TX
County
San Jacinto
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY TEXAS, INC.
Entity
MISO
Service Type
—
Point of Interconnection
Rivtrin - Staley 138kV Line #2 (Southern Line)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- TEXAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2897