MISO-J2899
250 MW hybrid in Calcasieu Parish, LA · In queue since September 2022 · Proposed COD April 2026
250 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 7m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-04-30
MISO-J2899 is a proposed 250 MW hybrid solar and battery project located in Calcasieu Parish, Louisiana. The project, which consists of 250 MW of solar generation, is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 14, 2022. The proposed commercial operation date is April 30, 2026.
The interconnection point is the Chalkley Co to Goos Ferry 230kV line, and the interconnecting utility is Entergy Louisiana. The project's interconnection agreement status is listed as "In Progress (unknown study)". The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
LA
County
Calcasieu Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY LOUISIANA
Entity
MISO
Service Type
—
Point of Interconnection
Chalkley Co to Goos Ferry 230kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.