MISO-J2901
140 MW generation in Columbia, AR · In queue since September 2022 · Proposed COD October 2027
140 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-01
MISO-J2901 is a proposed solar generation project with a total capacity of 140 MW, located in Columbia County, Arkansas. The project is being developed within the Entergy Arkansas service area and is interconnected to the Taylor - Macedonia 115 kV point of interconnection.
The project is currently active in the MISO interconnection queue, with an entry date of September 13, 2022, and a proposed commercial operation date of October 1, 2027. The interconnection agreement is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
AR
County
Columbia
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
Taylor - Macedonia 115 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2901