MISO-J2908
30 MW generation in Morgan, IL · In queue since July 2022 · Proposed COD July 2023
30 MW
Capacity
1
Components
Solar
3y 10m
In Queue
Cluster Study
IA Status
COD target: 2023
Total Duration
1 year
Schedule
34 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-07-30
MISO-J2908 is a proposed 30 MW solar generation project located in Morgan County, Illinois. The project is interconnected within the Midcontinent Independent System Operator (MISO) region to Ameren Illinois, and entered the MISO queue on July 27, 2022. Its proposed commercial operation date is July 30, 2023. The project's interconnection status is currently in the Cluster Study phase.
The proposed project consists of 30 MW of solar photovoltaic generation. The point of interconnection (POI) for the project is Jacksonville North. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
IL
County
Morgan
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Jacksonville North
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Jacksonville North Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.