MISO-J2913
90 MW storage in Sargent, ND · In queue since September 2022 · Proposed COD April 2025
90 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
2y 7m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-04-30
MISO-J2913 is a proposed 90 MW battery storage project located in Sargent County, North Dakota. The project, which is in the Midcontinent Independent System Operator (MISO) interconnection queue, entered the queue on September 15, 2022, and has a proposed commercial operation date of April 30, 2025. The interconnecting utility is Otter Tail Power Company.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the Forman 115kV Substation.
Generated from interconnection queue and public data sources
State
ND
County
Sargent
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
OTTER TAIL POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Forman 115kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Forman Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2913