MISO-J2917
80 MW generation in Ouachita Parish, LA · In queue since September 2022 · Proposed COD March 2026
80 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 6m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-01
MISO-J2917 is a proposed solar generation project with a total capacity of 80 MW, located in Ouachita Parish, Louisiana. The project is interconnected within the Midcontinent Independent System Operator (MISO) queue, having entered the queue on September 14, 2022. The proposed commercial operation date is March 1, 2026. The project's interconnection agreement status is currently "In Progress (unknown study)". Entergy Louisiana is listed as the utility.
The development project consists solely of solar photovoltaic generation. It is interconnected at the Prairie Road 115kV Substation. The project has appeared in recent news coverage regarding renewable energy projects in the MISO region.
Generated from interconnection queue and public data sources
State
LA
County
Ouachita Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY LOUISIANA
Entity
MISO
Service Type
—
Point of Interconnection
Prairie Road 115kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2917