MISO-J2944
350 MW generation in Portage, WI · In queue since September 2022 · Proposed COD April 2027
350 MW
Capacity
1
Components
Gas
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-01
MISO-J2944 is a proposed 350 MW gas-fired generation project located in Portage County, Wisconsin. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 15, 2022, and a proposed commercial operation date of April 1, 2027. The interconnection agreement status is listed as "In Progress (unknown study)".
The project is interconnected to the American Transmission Company via the Rocky Run - Garder Park 345 kV point of interconnection. The developer is not specified in the data.
Generated from interconnection queue and public data sources
State
WI
County
Portage
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Rocky Run - Garder Park 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2944