MISO-J2946
160 MW generation in Dubuque, IA · In queue since September 2022 · Proposed COD April 2027
160 MW
Capacity
1
Components
Gas
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-01
MISO-J2946 is a proposed 160 MW gas-fired generation project located in Dubuque County, Iowa. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 15, 2022, and a proposed commercial operation date of April 1, 2027. The project's interconnection point is the Salem - Hickory Creek 345 kV line, and its interconnection status is currently in the Cluster Study phase.
The proposed project is being developed within the ITC Midwest utility territory. It consists of a single 160 MW gas-fired component. The project is currently listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
IA
County
Dubuque
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
—
Point of Interconnection
Salem - Hickory Creek 345 kV line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM