MISO-J2948
75 MW generation in Marshall, IA · In queue since September 2022 · Proposed COD September 2024
75 MW
Capacity
1
Components
Gas
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2 years
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-01
The proposed MISO-J2948 project is a 75 MW natural gas generation facility located in Marshall County, Iowa. The project is in the MISO interconnection queue as of September 15, 2022, with a proposed commercial operation date of September 1, 2024. The interconnection utility is ITC Midwest, and the project's interconnection agreement status is currently in the Cluster Study phase.
The development project consists of 75 MW of gas-fired generation capacity. The point of interconnection (POI) is Marshalltown, Iowa.
Generated from interconnection queue and public data sources
State
IA
County
Marshall
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
—
Point of Interconnection
Marshalltown
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ALTW.MTOWNCT1
- POI Substation
- Marshalltown Substation