MISO-J2951
50 MW hybrid in Union, IA · In queue since September 2022 · Proposed COD June 2024
50 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
1y 9m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
The proposed MISO-J2951 project is a 50 MW solar and battery hybrid development in Union County, Iowa. Interconnecting to ITC Midwest, the project entered the MISO queue on September 5, 2022, with a proposed commercial operation date of June 1, 2024. The project's interconnection status is currently in the Cluster Study phase.
The hybrid project consists of 50 MW of solar generation capacity. The point of interconnection is the Creston Roadhouse substation.
Generated from interconnection queue and public data sources
State
IA
County
Union
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
—
Point of Interconnection
Creston Roadhouse
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Creston
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2951