MISO-J2952
100 MW generation in Chambers, TX · In queue since September 2022 · Proposed COD September 2026
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
MISO-J2952 is a proposed 100 MW solar generation project located in Chambers County, Texas. The project is being developed within the Entergy Texas service area and interconnected to the MISO grid at the Crooked Bayou to Stowell 138 kV Line. It entered the MISO interconnection queue on September 14, 2022, with a proposed commercial operation date of September 30, 2026.
The interconnection agreement status is currently listed as "In Progress (unknown study)". The project consists of 100 MW of solar photovoltaic generation capacity.
Generated from interconnection queue and public data sources
State
TX
County
Chambers
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY TEXAS, INC.
Entity
MISO
Service Type
—
Point of Interconnection
Crooked Bayou to Stowell 138 kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- TEXAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.