MISO-J2957
100 MW hybrid in Panola, MS · In queue since September 2022 · Proposed COD January 2027
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-01
MISO-J2957 is a proposed 100 MW hybrid solar and battery energy storage project located in Panola County, Mississippi. The project, which consists of 100 MW of solar capacity, is in the Midcontinent Independent System Operator (MISO) interconnection queue.
The project entered the MISO queue on September 15, 2022, with a proposed commercial operation date of January 1, 2027. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The proposed point of interconnection (POI) is the Como - Crenshaw 115 kV Line, and the interconnecting utility is Entergy Mississippi, LLC.
Generated from interconnection queue and public data sources
State
MS
County
Panola
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
—
Point of Interconnection
Como - Crenshaw 115 kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2957