MISO-J2966
450 MW generation in Quitman, MS · In queue since September 2022 · Proposed COD October 2025
450 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 1m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-15
MISO-J2966 is a proposed solar generation project with a total capacity of 450 MW, located in Quitman County, Mississippi. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 8, 2022, and a proposed commercial operation date of October 15, 2025. The interconnecting utility is Entergy Mississippi, LLC.
The interconnection agreement (IA) status for MISO-J2966 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Batesville to Moon Lake substation 230kV line. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
MS
County
Quitman
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
—
Point of Interconnection
Batesville to Moon Lake ss 230kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Batesville
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.