200 MW generation in Jefferson Davis Parish, LA · In queue since September 2022 · Proposed COD October 2025
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 1m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-15
MISO-J2967 is a proposed 200 MW solar generation project located in Jefferson Davis Parish, Louisiana. The project, under consideration by Entergy Louisiana, entered the MISO interconnection queue on September 9, 2022, with a proposed commercial operation date of October 15, 2025. Its interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project consists of 200 MW of solar photovoltaic generation. The point of interconnection is the Lowe Grout Rd to Jennings 138kV Line.
Generated from interconnection queue and public data sources
State
LA
County
Jefferson Davis Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY LOUISIANA
Entity
MISO
Service Type
—
Point of Interconnection
Lowe Grout Rd to Jennings 138kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.