Project MISO-J2983 — Project Summary

Queue ID
MISO-J2983
Capacity
150 MW
Technology
Solar
Status
active
Location
Grant, AR
Region
MISO
Developer
IA Status
In Progress (unknown study)

MISO-J2983

MISO-J2983BetaActiveSolarMISOLBNL + Live

150 MW generation in Grant, AR · In queue since September 2022 · Proposed COD September 2025

150 MW

Capacity

1

Components

Solar

3y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection

Total Duration

3 years

Schedule

8 months past proposed COD

In Study38%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-09-15

About

MISO-J2983 is a proposed solar generation project with a total capacity of 150 MW, located in Grant County, Arkansas. The development project is interconnected within the Midcontinent Independent System Operator (MISO) queue, with an initial queue entry date of September 15, 2022. Entergy Arkansas is the utility associated with the project.

The proposed commercial operation date (COD) for MISO-J2983 is September 15, 2025. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Woodward- AECC Grapevine 115 Kv.

Generated from interconnection queue and public data sources

Project Details

State

AR

County

Grant

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

ENTERGY ARKANSAS

Entity

MISO

Service Type

Point of Interconnection

Woodward- AECC Grapevine 115 Kv

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
ARKANSAS.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J2983