MISO-J2985
150 MW generation in Chicot, AR · In queue since September 2022 · Proposed COD September 2025
150 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3 years
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-15
MISO-J2985 is a proposed solar generation project with a total capacity of 150 MW, located in Chicot County, Arkansas. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 15, 2022, and a proposed commercial operation date of September 15, 2025. The interconnecting utility is Entergy Arkansas.
The interconnection agreement (IA) status for MISO-J2985 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Chicot - Eudora 115kV Line. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
AR
County
Chicot
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
Chicot - Eudora 115kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2985