MISO-J2989
200 MW generation in Hardin, IA · In queue since September 2022 · Proposed COD June 2025
200 MW
Capacity
1
Components
Wind
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
2y 9m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-15
MISO-J2989 is a proposed 200 MW wind generation project located in Hardin County, Iowa. The project, which consists of 200 MW of wind capacity, is in the Midcontinent Independent System Operator (MISO) interconnection queue. The queue entry date is September 14, 2022, with a proposed commercial operation date of June 15, 2025. The interconnection utility is ITC Midwest, and the point of interconnection is the Blackhawk (MEC)- Quinn 345 KV substation. The project's interconnection status is currently in the Cluster Study phase.
Generated from interconnection queue and public data sources
State
IA
County
Hardin
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
—
Point of Interconnection
Blackhawk (MEC)- Quinn 345 KV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2989