MISO-J2997
175 MW storage in Livingston, MI · In queue since September 2022 · Proposed COD September 2025
175 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3 years
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-15
MISO-J2997 is a proposed 175 MW battery storage project located in Livingston County, Michigan. The project is interconnected within the Midcontinent Independent System Operator (MISO) region and is being managed by utility ITC. The project entered the MISO interconnection queue on September 14, 2022, with a proposed commercial operation date of September 15, 2025.
The interconnection agreement (IA) for MISO-J2997 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Colfax - Madrid 120kV line. The development project consists solely of battery storage, with a total capacity of 175 MW.
Generated from interconnection queue and public data sources
State
MI
County
Livingston
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
Colfax - Madrid 120kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2997