MISO-J3002
325 MW hybrid in Pine, MN · In queue since September 2022 · Proposed COD August 2025
325 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
2y 11m
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-08-30
MISO-J3002 is a proposed 325 MW hybrid solar and battery energy storage project located in Pine County, Minnesota. The project, which consists of 325 MW of solar generation, is in the Midcontinent Independent System Operator (MISO) interconnection queue. The queue entry date is September 15, 2022, with a proposed commercial operation date of August 30, 2025.
The interconnection request is currently in the Cluster Study phase. The point of interconnection is the Arrowhead - Bear Creek (GRE) 230 kV line. The interconnecting utility is Minnesota Power Inc.
Generated from interconnection queue and public data sources
State
MN
County
Pine
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MINNESOTA POWER INC.
Entity
MISO
Service Type
—
Point of Interconnection
Arrowhead - Bear Creek (GRE) 230 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3002