MISO-J3014
300 MW generation in Rapides Parish, LA · In queue since September 2022 · Proposed COD October 2026
300 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-31
MISO-J3014 is a proposed 300 MW solar generation project located in Rapides Parish, Louisiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue as of September 15, 2022, with a proposed commercial operation date of October 31, 2026. The interconnecting utility is CLECO POWER.
The project's interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
LA
County
Rapides Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CLECO POWER
Entity
MISO
Service Type
—
Point of Interconnection
Cooper to Leesville 138kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3014